This page reports that Tokyo Electric Power applied to the Nuclear Regulation Authority to conduct a final inspection for commercial operation of Kashiwazaki-Kariwa Nuclear Power Station Unit 6 (Niigata Prefecture) on April 16. A warning system activated on March 12 due to component damage, causing power generation to stop for about a week. After investigation, the actual cause was found to be a broken component connecting the generator to the earth, not a leakage. The component was replaced and power generation resumed on March 22.